What are dummy activities?
A. Activities in PDM which are not necessary and can be dropped if time is running out.
B. Arrows in ADM which represent dependencies between nodes without real activities.
C. Activities, which can be passed to the team members with the lowest IQ.
D. Activities in PDM which are not performed by team members.