What should the manager do first with aggressive schedule?

posted 2½years ago by pin
© Copyright: Oliver F. Lehmann PMP Self Test, oliverlehmann.com
Time Management

You are assigned as the project manager in a project with an aggressive schedule. During a recent meeting your team complained about the high pressure applied and the many hours of overwork time. What should you do first?

A. Try to obtain additional budget and time.
B. Improve team communication and availability of high quality data on risks. Use this information to enable you to make well-founded decisions earlier.
C. The problem might be the customer disturbing project rhythm. Keep him on distance from the team.
D. Apply fast tracking to shorten project duration without additional work.

george (2¼years ago):
I think it's D, because:

A: It's a good option, but should be considered second
B: This option won't immediately change the schedule
C: Maybe this is a problem, but the key root cause is the schedule