A document called ____________ is created by decomposing the project scope into smaller, more manageable elements.

posted 2¾years ago by pin
© Copyright: Oliver F. Lehmann PMP Self Test, oliverlehmann.com

A document called ____________ is created by decomposing the project scope into smaller, more manageable elements.

A. Scope Statement
B. Network Logic Diagram
C. Work Breakdown Structure
D. Requested Change

george (2½years ago):
Answer is C.

A: Scope Statement is a scope definition document, nothing about decomposition
B: I know about "Network Diagram", nothing about Network Logic Diagram
D: Requested Change is a specification of a required change