Which stage of team development can be difficult to overcome in such a situation?

posted 14½months ago by pin
© Copyright: Oliver F. Lehmann PMP Self Test, oliverlehmann.com
Conflicts | Human Resource Management

Your project management team includes two external consultants each from a different company. You found that repeated conflicts between the two consultants already slow down project progress and jeopardize achievement of objectives.

Which stage of team development can be difficult to overcome in such a situation?

A. Storming from Forming, Storming, Norming, Performing
B. Panic from Enthusiasm, Panic, Hope, Solution
C. Kickoff from Assignment, Kickoff, Training, Communicating
D. Frustration from Direction, Frustration, Cooperation, Collaboration

(c) 2009-2010 thePMP.com, rev.343, 0.22sec