Which of the following process is not included in project communication knowledge area?

posted 2½years ago by pin
© Copyright: preparepm.com, Mock Exam
Communications Management

Which of the following process is not included in project communication knowledge area?

A. Documenting Project Closure
B. Plan Communications
C. Distribute Information
D. Managing Stakeholder Expectations

george (2¼years ago):
It's A. All other processes are inside communication management knowledge area.