How many channel of communications are there between these stakeholders?

posted 14½months ago by pin
© Copyright: preparepm.com, Mock Exam
Communication Channels | Communications Management | Stakeholders

The project you are managing has nine stakeholders. How many channel of communications are there between these stakeholders?

A. 9
B. 8
C. 45
D. 36

george (10¾months ago):
The formula is N * (N-1) / 2, so the answer is 36.