posted 2½years ago by pin
© Copyright: preparepm.com, Mock Exam
Communication Channels | Communications Management | Stakeholders
The project you are managing has nine stakeholders. How many channel of communications are there between these stakeholders?
A. 9
B. 8
C. 45
D. 36
george (2¼years ago):
The formula is N * (N-1) / 2, so the answer is 36.
(c) 2009-2012 thePMP.com, rev.346, 0.40sec