Which negotiation strategy is used?

posted 2¾years ago by Illia
© Copyright: Rita Mulcahy, PMP Exam Prep, Rita's Course in a Book for Passing the PMP Exam, Fifth Edition, RMC Publications Inc. (2005), page 401, question 20
Procurement Management

You are in the middle of a complex negotiation when the other party says, "We need to finish in one hour because I have to catch my plane." That person is using which of the following negotiation strategies?

A. Good guy, bad guy
B. Delay
C. Deadline
D. Extreme demands

george (2¾years ago):
My suggestion is C

A: "Good guy/Bad guy" assumes that there is someone else in the negotiation, who offers much worse conditions. For example: "We need to finish now because otherwise my boss cancels everything"

B: "Delay" means that the bad guy is time, for example: "We need to finish now otherwise I will be here only in 3 months"

D: "Extreme demands" would look like: "We need to finish now or the price is twice higher tomorrow"