Which of the following is not normally an element of the Project Charter?
A. The formal authorization to apply organizational resources to project activities.
B. Work package descriptions.
C. The business need that the project was undertaken to address.
D. The product description or a reference to this document
george (2½years ago):
Work package descriptions are not part of project charter, they are part of work breakdown structure (WBS) document. The answer is B