What should not be part of a risk management plan?
A. Roles and responsibilities for handling risks
B. Timing of risk management activities
C. The managerial approach towards risk
D. Individual risks
george (2½years ago):
Individual risks are not part of a risk management plan, answer is D. All other options could be part of risk management planning.