Which of the following is displayed as an S-curve?

posted 2¼years ago by Natalie2000
© Copyright: Project Management Professional (PMP) Study Guide by Kim Heldman, Sybex Inc., Alameda, CA, USA, 2002, page 283, question 19

Which of the following is displayed as an S-curve?
A. Gantt
B. Cost baseline
C. Critical path
D. PERT

Vorobey (18½months ago):
B. Cost baseline
which could be represented as S-curve whilst other answers appears irrelevant

ksee00 (13months ago):
B. Cost baseline. S-Curve is on the format of reporting cost baseline performance.