You are working on the cost budget for this project. Which of the following is true?

posted 4¼months ago by Natalie2000
© Copyright: Project Management Professional (PMP) Study Guide by Kim Heldman, Sybex Inc., Alameda, CA, USA, 2002, page 283, question 18

You are the project manager for a custom home-building construction
company. You are working on the model home project for the upcoming
Show Homes Tour. The model home includes Internet connections
in every room and talking appliances. You are working on the cost
budget for this project. Which of the following is true?
A. This process assigns cost estimates to project activities including
risks and contingency plans.
B. The cost baseline will be used to measure variances and future
project performance.
C. This process assigns cost estimates for expected future period operating
costs.
D. The cost baseline is the expected cost for the project.

(c) 2010 thePMP.com, rev.301, 0.17sec