Obtaining formal project plan approval and sign-off is important for all of the following reasons except:
A. Stakeholders are able to recommend a project Planning methodology to follow throughout the remaining process groups.
B. Stakeholders are aware of the project details, which makes them more likely to participate in future project decisions.
C. Stakeholders will be more likely to cooperate.
D. Stakeholders are aware of the specific details regarding project schedules, budgets, and risks.
george ([WARNING] sprintf() [function.sprintf]: Too few arguments, file: /home/caybo/thepmp/library/FaZend/Application/functions.php(2) 1hrs ago):
I think that option A is not suitable here. Stakeholders don't need to recommend anything to the project manager.