posted 4¼months ago by Natalie2000
© Copyright: Project Management Professional (PMP) Study Guide by Kim Heldman, Sybex Inc., Alameda, CA, USA, 2002, page 281, question 12
You are the project manager working on a research project for a new
drug treatment. Your preliminary project schedule runs past the due
date for a federal grant application. The manager of the R&D department
has agreed to release two resources to work on your project in
order to meet the federal grant application date. This is an example of:
A. Crashing
B. Fast tracking
C. Resource leveling
D. Adjusting the resource calendar
(c) 2010 thePMP.com, rev.301, 0.15sec
PMP® and PMBOK® are registered trademarks of Project Management Institute, Inc.