You are the project manager working on a research project for a new
drug treatment. Your preliminary project schedule runs past the due
date for a federal grant application. The manager of the R&D department
has agreed to release two resources to work on your project in
order to meet the federal grant application date. This is an example of:
A. Crashing
B. Fast tracking
C. Resource leveling
D. Adjusting the resource calendar