If your expected value is 110 and the standard deviation is 12, which
of the following is true?
A. There is approximately a 99 percent chance of completing this
activity between 86 and 134 days.
B. There is approximately a 68 percent chance of completing this
activity between 98 and 122 days.
C. There is approximately a 95 percent chance of completing this
activity between 98 and 122 days.
D. There is approximately a 75 percent chance of completing this
activity between 86 and 134 days.