You are a project manager for a new software development project. You
have a few activities that require specialized testing. The testing might
need to be repeated more than once. Which of the following do you
choose?
A. The Graphical Evaluation and Review Technique because it allows
for conditional branching and looping for the testing activity
B. The Critical Path Method because it allows for float time to be calculated
for the testing activity
C. The Program Evaluation and Review Technique because it allows
for conditional branching and looping for the testing activity
D. The Program Evaluation and Review Technique because it allows
for a weighted average distribution, which will even out the time
needed for the testing activity