Which of the following is true regarding the critical path?

posted 2¼years ago by Natalie2000
© Copyright: Project Management Professional (PMP) Study Guide by Kim Heldman, Sybex Inc., Alameda, CA, USA, 2002, page 279, question 5
Critical Path | PERT

Which of the following is true regarding the critical path?
A. It should never be compressed.
B. It allows for looping and branching.
C. The critical path technique is the same as PERT.
D. It’s the duration of all tasks with zero float.