posted 4¼months ago by Natalie2000
© Copyright: Project Management Professional (PMP) Study Guide by Kim Heldman, Sybex Inc., Alameda, CA, USA, 2002, page 277, question 52
You are a project manager for Picture Shades, Inc. They manufacture
window shades for hotel chains that have replicas of Renaissance-era
paintings on the inside of the shades. Picture Shades is taking their
product to the home market, and you’re managing the new project.
They will offer their products at retail stores as well as on their website.
You’re developing the project schedule for this undertaking and
have determined the critical path. Which of the following is true?
A. You calculated the most likely start date and most likely finish
dates, float time, and weighted average estimates.
B. You calculated the activity dependency, and the optimistic and
pessimistic activity duration estimates.
C. You calculated the early and late start dates, early and late finish
dates, and float times for all activities.
D. You calculated the optimistic, pessimistic, and most likely duration
times and the float times for all activities.
(c) 2010 thePMP.com, rev.301, 0.18sec
PMP® and PMBOK® are registered trademarks of Project Management Institute, Inc.