posted 2¼years ago by Natalie2000
© Copyright: Project Management Professional (PMP) Study Guide by Kim Heldman, Sybex Inc., Alameda, CA, USA, 2002, page 277, question 1
Schedule | Time Management
The project schedule is used to determine all of the following except:
A. Cost estimates
B. Activity start dates
C. Float times
D. Activity end dates
george (17¼months ago):
I think it's B. Project schedule is created when activities are identified, their durations (option D), estimates (options A) and dependencies (option C) are identified. Project schedule helps project manager to allocated activities on a calendar.
(c) 2009-2012 thePMP.com, rev.346, 0.35sec
PMP® and PMBOK® are registered trademarks of Project Management Institute, Inc.