The project schedule is used to determine all of the following except:
A. Cost estimates
B. Activity start dates
C. Float times
D. Activity end dates
george (24hrs ago):
I think it's B. Project schedule is created when activities are identified, their durations (option D), estimates (options A) and dependencies (option C) are identified. Project schedule helps project manager to allocated activities on a calendar.