You will outsource the production of this clothing line to a vendor. The vendor has requested a SOW.

posted 2¼years ago by Natalie2000
© Copyright: Project Management Professional (PMP) Study Guide by Kim Heldman, Sybex Inc., Alameda, CA, USA, 2002, page 240, question 20
Procurement Management | Statement Of Work | Vendor

You are the project manager for Heart of Texas casual clothing company. They’re introducing a new line of clothing called Black Sheep Ranch Wear. You will outsource the production of this clothing line to a vendor. The vendor has requested a SOW. All of the following are true except:

A. The SOW contains a description of the new clothing line.
B. As the purchaser, you are required to write the SOW.
C. The SOW contains the objectives of the project.
D. The vendor requires a SOW to determine if they can produce the clothing line given the very detailed specifications of this project.