Which of the following tools and techniques shows the impacts of one decision over another

posted 2¼years ago by Natalie2000
© Copyright: Project Management Professional (PMP) Study Guide by Kim Heldman, Sybex Inc., Alameda, CA, USA, 2002, page 138, question 12

Which of the following tools and techniques shows the impacts of one decision over another as well as the probability and cost of each risk along a logical path?

A. Simulation
B. Decision tree
C. Probability/impact risk matrix
D. Sensitivity analysis

george (2years ago):
I think that it's B — Decision Tree. Using this tool you can compare different decisions and analyze their impacts.