posted 4¼months ago by Natalie2000
© Copyright: Project Management Professional (PMP) Study Guide by Kim Heldman, Sybex Inc., Alameda, CA, USA, 2002, page 138, question 12
Which of the following tools and techniques shows the impacts of one decision over another as well as the probability and cost of each risk along a logical path?
A. Simulation
B. Decision tree
C. Probability/impact risk matrix
D. Sensitivity analysis
george (2½months ago): the answer is waiting for approval by moderator
(c) 2010 thePMP.com, rev.301, 0.16sec