Qualitative Risk Analysis | Risk Management
You are the project manager for a new website for the local zoo. You need to perform Qualitative Risk Analysis. When you’ve completed this process, you’ll produce all of the following outputs except:
A. Overall risk ranking for the project
B. List of prioritized risks
C. Inputs to other processes
D. List of risks for additional analysis and management
george (16¾months ago):
I would say it's D. Qualitative risk analysis won't produce any specific "list of risks", instead it gets risk list as an input and produce additional information in it, like risk probability, impact, score, ranking, etc.