Which of the following processes assess the likelihood of risk occurrences

posted 4¼months ago by Natalie2000
© Copyright: Project Management Professional (PMP) Study Guide by Kim Heldman, Sybex Inc., Alameda, CA, USA, 2002, page 237, question 9

Which of the following processes assess the likelihood of risk occurrences
and their consequences using numeric probability assignments?
A. Qualitative Risk Analysis
B. Risk Identification
C. Quantitative Risk Analysis
D. Risk Response Planning