You are installing a new accounting system and have identified several problems and their causes.

posted 2¼years ago by Natalie2000
© Copyright: Project Management Professional (PMP) Study Guide by Kim Heldman, Sybex Inc., Alameda, CA, USA, 2002, page 236, question 5
Quality Management

You are a project manager for Fountain of Youth Spring Water bottlers. You are installing a new accounting system and have identified several problems and their causes. You decide to use which of the following flowcharts to diagram the problems’ causes and effects?

A. Decision tree diagram
B. Fishbone diagram
C. Benchmark diagram
D. Simulation tree diagram

ksee00 (13months ago):
B. Fishbone diagram. The description is meant for fishbone diagram.

ksee00 (13months ago):
B. Fishbone diagram. The description is meant for fishbone diagram.