Which logical relationship does the PDM use most often?

posted 4¼months ago by Natalie2000
© Copyright: Project Management Professional (PMP) Study Guide by Kim Heldman, Sybex Inc., Alameda, CA, USA, 2002, page 187, question 20

Which logical relationship does the PDM use most often?
A. Start to finish
B. Start to start
C. Finish to finish
D. Finish to start