Your project’s primary constraint is quality.

posted 4¼months ago by Natalie2000
© Copyright: Project Management Professional (PMP) Study Guide by Kim Heldman, Sybex Inc., Alameda, CA, USA, 2002, page 186, question 18

Your project’s primary constraint is quality. In order to make certain
the project team members don’t feel too pressed for time and to avoid
schedule risk, you decide to use which of the following activity estimating
tools?
A. Expert judgment
B. Qualitatively based durations
C. Reserve time
D. Analogous estimating