Your project sponsor has requested a cost estimate for the project
you’re working on. This project is similar in scope to a project you
worked on last year. She would like to get the cost estimates as soon
as possible. Accuracy is not her primary concern right now. She needs
a ball park figure by tomorrow. You decide to use:
A. Analogous estimating techniques
B. Bottom-up estimating techniques
C. Parametric modeling techniques
D. Computerized modeling techniques