Your project sponsor has requested a cost estimate for the project. She
would like the cost estimate to be as accurate as possible as this might
be her one and only chance to secure the budget for this project due to
recent cuts in special projects. You decide:
A. To use analogous estimating techniques
B. To use bottom-up estimating techniques
C. To use top-down estimating techniques
D. To use expert judgment techniques