Which of the estimating techniques have you used?

posted 8years ago by Natalie2000
© Copyright: Project Management Professional (PMP) Study Guide by Kim Heldman, Sybex Inc., Alameda, CA, USA, 2002, page 185, question 14

You have been hired as a contract project manger for Grapevine Vineyards.
Grapevine wants you to design an Internet wine club for their
customers. One of the activities for this project is the installation and
testing of several new servers. You know from past experience it takes
about 16 hours per server to accomplish this task. Since you’re installing
10 new servers, you estimate this activity to take 160 hours. Which
of the estimating techniques have you used?
A. Analogous estimating
B. Bottom-up estimating
C. Qualitatively based durations
D. Reserve time