As project manager, you know that all of the following are true concerning analogous estimating techniques

posted 8years ago by Natalie2000
© Copyright: Project Management Professional (PMP) Study Guide by Kim Heldman, Sybex Inc., Alameda, CA, USA, 2002, page 184, question 12

As project manager, you know that all of the following are true concerning
analogous estimating techniques except:
A. It’s a qualitatively based estimating technique.
B. It’s a top-down estimating technique.
C. It’s a tool and technique of Activity Duration Estimating and Cost
Estimating.
D. It’s a form of expert judgment.