You have produced a project network diagram and have updated the activity list. Which process have you just finished?

posted 8years ago by Natalie2000
© Copyright: Project Management Professional (PMP) Study Guide by Kim Heldman, Sybex Inc., Alameda, CA, USA, 2002, page 184, question 10

You are the project manager for Changing Tides video games. You
have produced a project network diagram and have updated the activity
list. Which process have you just finished?
A. The Activity Sequencing process, which identifies all the specific
activities of the project
B. The Activity Sequencing process, which identifies all the activity
dependencies
C. The Activity Duration Estimating process, which diagrams project
network time estimates
D. The Activity Duration Estimating process,