All of the following are true regarding the tools and techniques of Activity Sequencing

posted 7¾years ago by Natalie2000
© Copyright: Project Management Professional (PMP) Study Guide by Kim Heldman, Sybex Inc., Alameda, CA, USA, 2002, page 183, question 9

All of the following are true regarding the tools and techniques of
Activity Sequencing except:
A. GERT uses analogous methods.
B. GERT allows for loops.
C. GERT is a conditional diagramming method.
D. GERT allows for conditional branches.