You have your activity list in hand and several time estimates and are ready to diagram the activity dependencies.

posted 7¾years ago by Natalie2000
© Copyright: Project Management Professional (PMP) Study Guide by Kim Heldman, Sybex Inc., Alameda, CA, USA, 2002, page 183, question 8

You are the project manager for Design Your Web Site, Inc. Your
company is designing the website for a national grocery store chain.
You have your activity list in hand and several time estimates and are
ready to diagram the activity dependencies. You should use which of
the following?
A. PDM techniques
B. PDM or ADM techniques
C. AON techniques
D. ADM techniques