You have your activity list in hand and are ready to diagram the activity dependencies using the PDM technique.

posted 10¼months ago by Natalie2000
© Copyright: Project Management Professional (PMP) Study Guide by Kim Heldman, Sybex Inc., Alameda, CA, USA, 2002, page 183, question 7
ADM | AOA | AON | Network Diagram | PDM

You are the project manager for Design Your Web Site, Inc. Your company is designing the website for a national grocery store chain. You have your activity list in hand and are ready to diagram the activity dependencies using the PDM technique. You know that:

A. PDM uses AON diagramming methods.
B. PDM uses AOA diagramming methods.
C. PDM uses ADM diagramming methods.
D. PDM uses PDM diagramming methods.

stantheman (2½weeks ago):
A: pdm is a method used in critical path methodology for constructing a project schedule network diagram. it uses boxes or rectangles, referred to as nodes, to represent activities and connects them with arrows to shows logical relationships that exist between them. the technique is know as activity on node.