Which of the following is true regarding the staffing management plan?

posted 2¼years ago by Natalie2000
© Copyright: Project Management Professional (PMP) Study Guide by Kim Heldman, Sybex Inc., Alameda, CA, USA, 2002, page 182, question 5
Human Resource Management | Staffing Management Plan

Which of the following is true regarding the staffing management plan?

A. It details the resource requirements and the quantity of resources needed for project activities. It is an output of the Resource Planning process.
B. It details how and when staff resources will be brought on and off the project. It is an output of the Organizational Planning process.
C. It details how and when staff resources will be brought on and off the project. It is an output of the Resource Planning process.
D. It details the resource requirements and the quantity of resources needed for project activities. It is an output of the Organizational Planning process.

george (2years ago):
I think it's B. Staffing management plan tells us how and where we're going to get resources we need, and don't say anything about particular resource requirements. The former are discussed in resource planning process.