You’ve constructed the WBS for your recent project.

posted 7¾years ago by Natalie2000
© Copyright: Project Management Professional (PMP) Study Guide by Kim Heldman, Sybex Inc., Alameda, CA, USA, 2002, page 151, question 19

You’ve constructed the WBS for your recent project. Level two assignments
have been made, and you’ve requested that the subproject managers
report back to you in 3 weeks with each of their individual WBSs
constructed. All of the following are true except:
A. The work package level facilitates resource assignments.
B. The work package level is the lowest level in the WBS.
C. The work package level defines the agreed-upon deliverables.
D. The work package level facilitates cost and time estimates.