All of the following are true regarding the WBS except

posted 7¾years ago by Natalie2000
© Copyright: Project Management Professional (PMP) Study Guide by Kim Heldman, Sybex Inc., Alameda, CA, USA, 2002, page 149, question 16

All of the following are true regarding the WBS except:
A. It is a deliverables-oriented grouping of project deliverables and
elements.
B. It defines and organizes the work of the project in a hierarchical form.
C. It provides a framework for the work of the project, and work not
shown on the WBS is not included in the project.
D. It defines all the deliverables of the project, but the activities level
should not be listed on the WBS.