The Scope Definition process is now complete. Which of the following is true?

posted 8years ago by Natalie2000
© Copyright: Project Management Professional (PMP) Study Guide by Kim Heldman, Sybex Inc., Alameda, CA, USA, 2002, page 149, question 15

Your company, Kick That Ball Sports, has appointed you project
manager for their new Cricket product line introduction. This is a
national effort, and all the retail stores across the country need to have
the new products on the shelves before the media advertising blitz
begins. The product line involves three new products, some with multiple
deliverables. The Scope Definition process is now complete.
Which of the following is true?
A. The WBS template, an output of the Scope Definition process, was
used from the previous project to create the WBS for this project.
The WBS encompasses the major deliverables for the project.
B. The WBS template from the previous project, an output from the
Scope Planning process, was used to create the WBS for this project.
The WBS encompasses the major deliverables for the project.
C. The WBS, an output of the Scope Planning process, has been created,
and it encompasses the full scope of work for the project.
D. The WBS, an output of the Scope Definition process, has been created,
and it encompasses the full scope of work for the project.