© Copyright: Project Management Professional (PMP) Study Guide by Kim Heldman, Sybex Inc., Alameda, CA, USA, 2002, page 79, question 15
Constraints | Cost Management | Time Management
You are a project manager working on a new software product your company plans to market to businesses. The project sponsor told you that the project must be completed by September 1. The company plans to demo the new software product at a trade show in late September and therefore needs the project completed in time for the trade show. However, the sponsor has also told you that the budget is fixed at $85,000 and cannot be increased by even $10 due to overall budget cuts this year. You must complete the project within the given time frame and budget. Which of the following is the primary constraint for this project?
A. Budget
B. Quality
C. Time
D. Schedule
george (9¾months ago): the answer was rejected by moderator
(c) 2009-2010 thePMP.com, rev.343, 0.23sec
PMP® and PMBOK® are registered trademarks of Project Management Institute, Inc.