Which of the following is true about new machine?

posted 2¼years ago by Natalie2000
© Copyright: Project Management Professional (PMP) Study Guide by Kim Heldman, Sybex Inc., Alameda, CA, USA, 2002, page 76, question 8
Assumptions | Constraints | Deliverables | Product Description

You work for a large manufacturing plant. You’re working on a new project for an overseas product release. This is the company’s first experience in the overseas market, and they hope to make a big splash with the introduction of this product. The project entails producing your product in a concentrated formula and packaging it in smaller containers than the U.S. product uses. A new machine is needed in order to mix the first set of ingredients in the concentrated formula. Which of the following is true?

A. The new machine, the concentrated formula, and the smaller package are each project constraints.
B. The new machine, the concentrated formula, and the smaller package description must be incorporated into the product description document.
C. The new machine, the concentrated formula, and the smaller package are each project assumptions.
D. The new machine, the concentrated formula, and the smaller package are each considered deliverables.

george (2years ago):
I think that both the machine and the formula are project deliverables. The answer is D.