posted 2½years ago by Illia
© Copyright: Rita Mulcahy, PMP Exam Prep, Rita's Course in a Book for Passing the PMP Exam, Fifth Edition, RMC Publications Inc. (2005), 103
Scope Change
After a large amount of effort, the project team has finally determined the specifications for a major scope change to the project. In light of this, what should the project manager do FIRST?
A. Look for other changes.
B. Notify the stakeholders about the new scope.
C. Gain sign-off on this change.
D. Calculate the risks associated with this change.
george (2½years ago):
Maybe D? PM should understand the impact of this change. Risks is an important part of the impact