Contracts | Product Description
When a project is being performed under contract, the product description is provided by which of the following?
A. The buyer
B. The project sponsor
C. The project manager
D. The contractor
george (2½years ago):
I think that it's A - the buyer. Answer C and D are not suitable at all, the project manager is not responsible for product description providing, the contractor - the same story.
Answer B is not correct, because project sponsor will not use the product, but will only sponsor its development.