The Project Integration Management knowledge area is made up of which of the following processes?

posted 2¼years ago by Natalie2000
© Copyright: Project Management Professional (PMP) Study Guide by Kim Heldman, Sybex Inc., Alameda, CA, USA, 2002, page 74, question 1
Integration Management

The Project Integration Management knowledge area is made up of which of the following processes?

A. Initiation, Project Plan Development, and Integrated Change Control
B. Project Plan Development, Project Plan Execution, and Integrated Change Control
C. Project Plan Development, Initiation, and Scope Planning
D. Initiation, Scope Planning, and Integrated Change Control

bbashir (14½months ago):
B. Project Plan Development, Project Plan Execution, and Integrated Change Control