Critical Path
Critical path tasks are those tasks that:
A. Have equal pessimistic, optimistic, and most likely estimated times
B. Have a float time of zero
C. Have the same start date
D. Have multiple early start dates and early finish dates
george (9½months ago):
The answer is B, see this explanation about critical path method (CPM).