posted 8¾months ago by Illia
© Copyright: Rita Mulcahy, PMP Exam Prep, Rita's Course in a Book for Passing the PMP Exam, Fifth Edition, RMC Publications Inc. (2005), 134
WBS
During a walk-through of a work package, you discover that a team member is completing the work differently than stated in the WBS dictionary. How should you deal with this?
A. Replace the team member.
B. Determine if the alternative way is acceptable to the functional manager.
C. Ask the team member if the changes are necessary.
D. Determine if the changes also change the scope of the work package.
george (8¾months ago):
I think it's D.
A: What will it give to the WBS, scope and project in general?
B: How does functional manager relate to this?
C: Why do we need an opinion of a team member? Is he/she in charge of a scope control?
D: If the scope is not changed - we may overlook this case.
(c) 2010 thePMP.com, rev.301, 0.21sec