© Copyright: Project Management Professional (PMP) Study Guide by Kim Heldman, Sybex Inc., Alameda, CA, USA, 2002, page 44, question 52
Historical Information | Project Selection Criteria | Strategic Plan
The product description, strategic plan, project selection criteria, and historical information are considered:
A. Inputs to the project Planning process
B. Inputs to the project Overview process
C. Inputs to the project Initiation process
D. Inputs to the project Execution process
george (2¼years ago):
I think these artifacts are inputs to Initiation Process, since they should exist before the project starts.