How the product description, strategic plan and project selection criteria, and historical information are considered?

posted 2¼years ago by Natalie2000
© Copyright: Project Management Professional (PMP) Study Guide by Kim Heldman, Sybex Inc., Alameda, CA, USA, 2002, page 44, question 52
Historical Information | Project Selection Criteria | Strategic Plan

The product description, strategic plan, project selection criteria, and historical information are considered:

A. Inputs to the project Planning process
B. Inputs to the project Overview process
C. Inputs to the project Initiation process
D. Inputs to the project Execution process

george (2¼years ago):
I think these artifacts are inputs to Initiation Process, since they should exist before the project starts.

(c) 2009-2012 thePMP.com, rev.346, 0.23sec
PMP® and PMBOK® are registered trademarks of Project Management Institute, Inc.