What are the Scope Planning process tools and techniques?
A. Benefit/cost analysis, work breakdown structure templates, expert judgment, and supporting detail
B. Product analysis, benefit/cost analysis, alternatives identification, and expert judgment
C. Product analysis, work breakdown structure templates, supporting detail, and expert judgment
D. Benefit/cost analysis, alternatives identification, supporting detail, and expert judgement
george (2¼years ago):
I think it's C because benefit/cost analysis is not in scope planning, but in integration management.