ADM | Network Diagram

All of the following are true regarding the ADM method except:

A. It’s a tool and technique of Activity Sequencing.
B. It uses one time estimate to determine durations.
C. It’s also called AOA.
D. It’s rarely used today.

george (2¼years ago):
I think the answer D is right. ADM is often used today. The rest is true. AOA means "Activity On Arrow".