According to the Guide to the PMBOK, the project manager is identified and assigned during which process?
A. As an input to the Initiation process
B. As an input to the Planning process
C. As an output of the Initiation process
D. As an output of the Scope Planning process
george (2¼years ago):
Project manager is assigned before any processes, thus, as an input to the Initiation Process, answer is A.