posted 9months ago by Illia
© Copyright: Rita Mulcahy, PMP Exam Prep, Rita's Course in a Book for Passing the PMP Exam, Fifth Edition, RMC Publications Inc. (2005), 95
Charter
You are taking over a project during the planning process group and discover that six individuals have signed the project charter. Which of the following should MOST concern you?
A.Who will be a member of the change control board
B.Spending more time on configuration management
C.Getting a single project sponsor
D.Determining the reporting structure
george (8¾months ago):
I think it's A.
B: Yes, a bit more, since we will have to create more accounts. But it's not very important.
C: Why do we care about project sponsor? If he/she/they pay - that's enough. No matter how many of them.
D: Yes, a bit more complex, but it's not critical
(c) 2010 thePMP.com, rev.301, 0.16sec
PMP® and PMBOK® are registered trademarks of Project Management Institute, Inc.