The Project Management Knowledge Areas:
A. Include Initiation, Planning, Executing, Controlling, and Closing
B. Consist of nine different areas that bring together processes that have things in common
C. Consist of five different processes that bring together phases of projects that have things in common
D. Include Planning, Executing, and Controlling processes as these three processes are commonly interlinked
george (9¾months ago):
It's B, there are 9 knowledge areas in PMBOK:
integration management,
cost management,
scope management,
time management,
risk management,
communications management,
human resource management,
procurement management
quality management